Project Programme Update September 2024
From where we are now to starting on site
Stage 1 of the tender process, Expression of Interest (EOI), has now closed and the Project Team are currently reviewing the returns. A shortlist of qualifying contractors from Stage 1 will proceed to Stage 2, the Invitation to Tender (ITT), and the Project Team anticipate completing evaluations of Stage 2 returns early November.
The final shortlist of at least two bids, along with estimated costs for the recoverable elements of the works, will be included in the statutory Section 20 Leaseholder consultation process.
At the end of the 35 day Section 20 consultation, a report on the outcome of the procurement exercise will be produced. This will then be presented to Children and Community Services (CCS) Committee recommending an award of contract.
The report must be available to members two weeks in advance of the meeting. The Project Team have earmarked the January 2025 Committee which means the report will need to be finalised before Christmas 2024. There is a recognition that this is a very tight schedule and the Project Team are working hard to avoid delays. However, should protracted clarifications with prospective contractors be required to provide the appropriate assurances over the robustness of submitted pricing then a short delay until the March Committee may be required.
City of London recoverable costs (recharges to leaseholders)
The Quantity Surveyor has provided the City of London Corporation Legal Department with a cost schedule for an opinion as to what elements are recoverable from Leaseholders. A report will then be presented to CCS Committee for approval.
Once the decision has been made on which elements are recoverable and the tender process complete the Project Manager will then present a schedule of those estimated costs to the Home Ownership team who will then deduct any abatements and apply each leaseholder’s dwelling % in order to arrive at the individual estimated costs for the Section 20 notice.